Hawthorn Solar Park
Application Report — Gate 2 Large Generation Export
Ready with flagsEvidence citedHuman review required
ϟ
Requested Export
160 MW
⌬
Connection Node
Fleet BSP
⛓
Technical Pathway
Type D / Grid Code
⚖
Current Recommendation
Defer
Readiness Assessment
✓Land rights
Option agreement provides control of the land option area.
PassLR-12 ↗⌄✓Planning
Development application pathway identified and feasible.
PassPL-04 ↗⌄⚑Technical pathway
Type D pathway requires network impact assessment.
FlagTP-07 ↗⌄✓Export compliance
Requested export within cohort capacity at Fleet BSP.
PassEX-03 ↗⌄⚑Deliverability
Reinforcement timing likely post-2032; project schedule risk.
Pass with minor riskDL-02 ↗⌄Document Bundles
▤Land Control Bundle
3 docs
Land option, title search, easements
✓ Complete
▤Planning Bundle
2 docs
Planning report, zoning verification
✓ Complete
▤Technical Bundle
4 docs
Connection study, one-line diagram, studies
✓ Complete
▤Deliverability Bundle
2 docs
Construction plan, program risk assessment
✓ Complete
Deficiencies & Risks
!Cohort export conflict at Fleet BSP
Current cohort commitments exceed available export capacity at Fleet BSP.
BlockingBlocks progression›Current cohort commitments exceed available export capacity at Fleet BSP.
!Grid Code interface requires engineer confirmation
Type D technical requirements not fully confirmed with network operator.
MediumDelays decision›Type D technical requirements not fully confirmed with network operator.
!Reinforcement window likely post-2032
Indicative program suggests reinforcement available post-2032.
MediumSchedule risk›Indicative program suggests reinforcement available post-2032.