GridLayer Operator View
Simulated SEPD South
Synthetic Data
?
AL

Tranche Network Screen

Cohort export assessment — Gate 2 Large Generation Export

11 applications in screenEvidence groundedHuman review required
Projects in Tranche
11
ϟ
Requested Export
1,345 MW
Available Headroom
980 MW
Conflict Nodes
2

Cohort Capacity Map

!Fleet BSP
Headroom
310 MW
Requested
352 MW
Over by
42 MW
Over capacity
Fleet Edge Solar90 MW
Hawthorn Solar Park160 MW
Seaview Solar102 MW
Longfield 275kV
Headroom
240 MW
Requested
180 MW
Within headroom
Maple Ridge 132kV
Headroom
180 MW
Requested
165 MW
Near capacity
Carradale 275kV
Headroom
250 MW
Requested
290 MW
Constraint flag
Longfield Solar120 MW
Northfield Solar110 MW
Alder Down Solar150 MW
Seaview Solar75 MW
Cranford Solar200 MW
Hawthorn Solar Park160 MW

Node Comparison

NodeHeadroomRequestedResultRecommendation
!Fleet BSP310 MW352 MWOver capacityDefer Hawthorn / phase export
Longfield 275kV240 MW180 MWWithin headroomApprove
Maple Ridge 132kV180 MW165 MWNear capacityConditional
!Carradale 275kV250 MW290 MWConstraint flagEscalate to study