GridLayer Operator View
UK DNO 1

Bernierburgh Wind Scheme

Application Details — Gate 2 Large Generation Export (TAC-2026-0002)

Executive Summary

conditional recommendation pack · ready for engineer

Bernierburgh Wind Scheme (TAC-2026-0002): READY WITH FLAGS. 45 flags noted but do not block tranche inclusion.

Requested Export
236 MW
Connection Node
Murazikland GSP
Technical Pathway
D / BEGA
Current Recommendation
Pending

Readiness Assessment

Land plan boundary consistent

Risk identified against LE004 (land_environment).

Site boundary, red line plan, cable route, land registry parcels, and planning drawings must be internally consistent.

land_rights_agent · Land plan boundary consistent · 79% confidence

Fail
Third-party rights identified

Risk identified against LE005 (land_environment).

Project must disclose restrictive covenants, mineral rights, access rights, grazing rights, public rights of way, and affected third-party interests.

land_rights_agent · Third-party rights identified · 80% confidence

Fail
Noise and vibration assessment provided

Risk identified against LE020 (land_environment).

Project must assess construction and operational noise, vibration, sensitive receptors, transformer/inverter noise, and mitigation.

land_rights_agent · Noise and vibration assessment provided · 65% confidence

Fail
Climate change assessment provided

Risk identified against LE021 (land_environment).

Environmental submission must assess greenhouse gas effects, climate resilience, future weather risks, and adaptation measures.

land_rights_agent · Climate change assessment provided · 66% confidence

Fail
Socio-economic assessment provided

Risk identified against LE022 (land_environment).

Project must assess local employment, supply chain, community effects, land-use effects, and socio-economic mitigation or benefits.

land_rights_agent · Socio-economic assessment provided · 66% confidence

Fail
Human health assessment provided

Risk identified against LE023 (land_environment).

Project must assess potential health effects from noise, air quality, traffic, fire risk, construction disruption, and operational hazards.

land_rights_agent · Human health assessment provided · 66% confidence

Fail
Glint and glare assessed

Risk identified against LE024 (land_environment).

A glint/glare assessment must be present for relevant receptor classes, including homes, roads, railways, aviation, and public rights of way.

land_rights_agent · Glint and glare assessed · 67% confidence

Fail
SCADA and communications design defined

Risk identified against CN010 (connection).

Project must define telemetry, SCADA, command/control, communications routes, latency, availability, and cybersecurity assumptions.

technical_classification_agent · SCADA and communications design defined · 65% confidence

Fail
Supplier is a valid trading company

Risk identified against PR001 (procurement).

Major equipment supplier must be a valid registered company with no unresolved dissolution, insolvency, or sanctions flags.

readiness_orchestrator · Supplier is a valid trading company · 67% confidence

Fail
Supplier liquidity checked

Risk identified against PR002 (procurement).

Procurement pack must include liquidity, credit, or going-concern checks for major equipment suppliers and EPC counterparties.

readiness_orchestrator · Supplier liquidity checked · 68% confidence

Fail
Procurement agreement valid through construction start

Risk identified against PR003 (procurement).

Supply, reservation, or framework agreement must remain in date through construction start or include renewal rights.

readiness_orchestrator · Procurement agreement valid through construction start · 68% confidence

Fail
Commissioning plan provided

Risk identified against CO007 (construction).

Project must include commissioning, testing, witness testing, energisation, and handover steps with accountable owners.

readiness_orchestrator · Commissioning plan provided · 87% confidence

Fail
Sanctions screening complete

Risk identified against LC004 (legal_compliance).

Sponsors, counterparties, beneficial owners, suppliers, and agents must pass sanctions screening.

readiness_orchestrator · Sanctions screening complete · 85% confidence

Fail
O&M provider identified

Risk identified against OP001 (operations).

Project must identify operations and maintenance provider or state procurement path, scope, response times, and capability requirements.

readiness_orchestrator · O&M provider identified · 66% confidence

Fail
Availability assumptions supported

Risk identified against OP002 (operations).

Operational model must support availability assumptions with warranty, maintenance, failure-rate, degradation, and outage assumptions.

readiness_orchestrator · Availability assumptions supported · 67% confidence

Fail
Spare parts strategy provided

Risk identified against OP003 (operations).

Project must identify critical spares, lead times, warranty replacement process, and minimum stock requirements.

readiness_orchestrator · Spare parts strategy provided · 67% confidence

Fail
Monitoring and reporting defined

Risk identified against OP004 (operations).

Project must define performance monitoring, reporting cadence, data ownership, alarms, KPIs, and operator interfaces.

readiness_orchestrator · Monitoring and reporting defined · 67% confidence

Fail
Decommissioning responsibility assigned

Risk identified against OP005 (operations).

Project must identify accountable party, budget assumptions, recycling obligations, land restoration, and end-of-life process.

readiness_orchestrator · Decommissioning responsibility assigned · 68% confidence

Fail
Outage window coordination evidenced

Risk identified against GC005 (grid_consultation).

Project must identify outage requirements, network access windows, commissioning constraints, and operator coordination status.

export_compliance_agent · Outage window coordination evidenced · 84% confidence

Fail
Land agreement valid through construction start

Risk identified against LE002 (land_environment).

Land agreement must remain active through construction start or include extension rights sufficient for delivery milestones.

land_rights_agent · Land agreement valid through construction start · 79% confidence

Flag
Right-of-way plan provided

Risk identified against LE003 (land_environment).

Project must include right-of-way, access, easement, wayleave, and cable route evidence for construction and operation.

land_rights_agent · Right-of-way plan provided · 79% confidence

Flag
Statement of need provided

Risk identified against PL005 (planning).

Submission must explain project need, technology purpose, grid benefit, capacity contribution, and alignment with energy policy.

planning_agent · Statement of need provided · 87% confidence

Flag
Procurement spec declares grid-forming capability

Risk identified against PR005 (procurement).

Inverter/PCS technical schedules must state grid-forming operation where required; grid-following only is flagged as a stability risk.

readiness_orchestrator · Procurement spec declares grid-forming capability · 69% confidence

Flag
Grid-following risk treatment disclosed

Risk identified against PR006 (procurement).

Where equipment is grid-following, a mitigation statement and residual risk declaration must be present.

readiness_orchestrator · Grid-following risk treatment disclosed · 69% confidence

Flag
Expansion capacity reserved where required

Risk identified against PR007 (procurement).

Procurement design must confirm whether transformers, inverters, switchgear, civil pads, ducts, and control systems preserve future expansion capacity.

readiness_orchestrator · Expansion capacity reserved where required · 69% confidence

Flag
Cyber security requirements included

Risk identified against PR009 (procurement).

SCADA, EMS, inverter, metering, and remote-access suppliers must evidence cyber-security requirements and access controls.

readiness_orchestrator · Cyber security requirements included · 70% confidence

Flag
Developer experience evidenced

Risk identified against PE001 (personnel).

Developer must evidence prior delivery experience for projects of comparable technology, capacity, complexity, or jurisdiction.

readiness_orchestrator · Developer experience evidenced · 73% confidence

Flag
Principal designer and contractor named

Risk identified against PE003 (personnel).

Project must identify principal designer, principal contractor, and accountable CDM duty holders before construction readiness approval.

readiness_orchestrator · Principal designer and contractor named · 74% confidence

Flag
Grid engineering lead assigned

Risk identified against PE004 (personnel).

Project must name the accountable grid engineering lead responsible for connection data, technical submissions, studies, and operator engagement.

readiness_orchestrator · Grid engineering lead assigned · 74% confidence

Flag
Environmental consultant appointed

Risk identified against PE005 (personnel).

Project must evidence appointment of a competent environmental adviser for ecology, flood, heritage, landscape, and EIA coordination where applicable.

readiness_orchestrator · Environmental consultant appointed · 74% confidence

Flag
Responsibility matrix complete

Risk identified against PE006 (personnel).

Delivery governance must include a RACI or equivalent responsibility matrix for grid, land, planning, procurement, construction, financing, and compliance.

readiness_orchestrator · Responsibility matrix complete · 75% confidence

Flag
Material contracts signed or statused

Risk identified against LC003 (legal_compliance).

Land, grid, EPC, equipment, financing, O&M, offtake, and insurance contracts must be signed or clearly statused with blockers.

readiness_orchestrator · Material contracts signed or statused · 85% confidence

Flag
Data room index complete

Risk identified against LC005 (legal_compliance).

Project must include an indexed data room or document register mapping every required evidence item to a latest-version document.

readiness_orchestrator · Data room index complete · 86% confidence

Flag
Hazard identification complete

Risk identified against SA001 (safety).

Project must include hazard identification for construction, energisation, operation, fire, electrical safety, public access, and emergency response.

readiness_orchestrator · Hazard identification complete · 73% confidence

Flag
Electrical safety rules defined

Risk identified against SA002 (safety).

Project must define electrical safety rules, isolation procedures, lockout/tagout approach, authorised persons, and operational boundaries.

readiness_orchestrator · Electrical safety rules defined · 73% confidence

Flag
Emergency response plan provided

Risk identified against SA003 (safety).

Emergency response plan must cover fire, flood, security breach, electrical incident, severe weather, and grid outage scenarios.

readiness_orchestrator · Emergency response plan provided · 73% confidence

Flag
Site security plan provided

Risk identified against SA004 (safety).

Project must include fencing, CCTV, access control, signage, lighting, cyber-physical security, and public safety measures.

readiness_orchestrator · Site security plan provided · 74% confidence

Flag
Safety zone assessment provided

Risk identified against SA005 (safety).

Project must assess required safety zones, separation distances, public rights of way, nearby receptors, and operational access constraints.

readiness_orchestrator · Safety zone assessment provided · 74% confidence

Flag
Evidence freshness checked

Risk identified against RD003 (readiness).

Critical documents must be current, not superseded, and within validity windows at the relevant project milestone.

readiness_orchestrator · Evidence freshness checked · 91% confidence

Flag
Connection offer status declared

Risk identified against GC003 (grid_consultation).

Project must declare whether connection offer is requested, received, accepted, expired, modified, or awaiting queue reform impact.

export_compliance_agent · Connection offer status declared · 83% confidence

Flag
Deliverability pack minimal

Deliverability bundle has no programme document attached.

No deliverability documents detected at this revision.

deliverability_agent · Deliverability pack minimal · 70% confidence

Flag
Insurance in force

Liability and construction insurance in force

Certificate schedule shows current cover.

insurance_agent · Insurance in force · 95% confidence

Pass
16 documents classified

All uploaded documents auto-classified with confidence ≥ 0.85.

Filename and contents heuristics matched expected document families.

document_classifier · 16 documents classified · 94% confidence

Pass
Funding statement provided

Pass against FI001 (financing).

Application must include a funding statement showing committed, conditional, or proposed sources of capital.

finance_agent · Funding statement provided · 91% confidence

Pass
Sources and uses balance

Pass against FI002 (financing).

Financial model must show that committed and expected funding sources cover development, construction, grid, contingency, and financing costs.

finance_agent · Sources and uses balance · 91% confidence

Pass
Grid connection costs included

Pass against FI003 (financing).

Financial model must include connection offer securities, contestable works, non-contestable works, reinforcement costs, and milestone liabilities.

finance_agent · Grid connection costs included · 92% confidence

Pass
Construction contingency above threshold

Pass against FI004 (financing).

Budget must include a stated contingency allowance appropriate to stage, technology, and procurement maturity.

finance_agent · Construction contingency above threshold · 92% confidence

Pass
Lender due diligence status declared

Pass against FI005 (financing).

Submission must state whether technical, legal, insurance, tax, grid, and environmental due diligence has started, completed, or remains outstanding.

finance_agent · Lender due diligence status declared · 92% confidence

Pass
Revenue assumptions supported

Pass against FI006 (financing).

Revenue model must cite basis for price, PPA, tolling, merchant, capacity market, ancillary services, or curtailment assumptions.

finance_agent · Revenue assumptions supported · 93% confidence

Pass
AML checks complete

Pass against FI007 (financing).

Sponsors, major shareholders, lenders, and material counterparties must pass anti-money laundering and sanctions screening.

finance_agent · AML checks complete · 93% confidence

Pass
Anti-corruption declaration provided

Pass against FI008 (financing).

Project must include anti-bribery and anti-corruption declarations for sponsors, agents, land intermediaries, and procurement counterparties.

finance_agent · Anti-corruption declaration provided · 93% confidence

Pass
Land ownership, lease, or option evidenced

Pass against LE001 (land_environment).

Project must evidence land ownership, purchase agreement, lease, option to lease, or exclusivity rights covering the project footprint.

land_rights_agent · Land ownership, lease, or option evidenced · 78% confidence

Pass
Reinstatement and decommissioning plan provided

Pass against LE006 (land_environment).

Project must include land reinstatement, decommissioning, restoration, and financial provision assumptions where applicable.

land_rights_agent · Reinstatement and decommissioning plan provided · 80% confidence

Pass
Landscape and visual impact assessment provided

Pass against LE007 (land_environment).

Project must assess landscape character, visual receptors, cumulative effects, viewpoints, and mitigation.

land_rights_agent · Landscape and visual impact assessment provided · 80% confidence

Pass
Historic environment assessment provided

Pass against LE008 (land_environment).

Project must assess listed buildings, scheduled monuments, archaeology, conservation areas, setting impacts, and mitigation.

land_rights_agent · Historic environment assessment provided · 81% confidence

Pass
Ecology and nature assessment provided

Pass against LE009 (land_environment).

Ecology submission must assess habitats, designated sites, protected species, mitigation hierarchy, and residual effects.

land_rights_agent · Ecology and nature assessment provided · 81% confidence

Pass
Protected species plan provided

Pass against LE010 (land_environment).

Project must include survey results, avoidance measures, mitigation, licensing status, and monitoring for protected species.

land_rights_agent · Protected species plan provided · 88% confidence

Pass
Biodiversity net gain assessment provided

Pass against LE011 (land_environment).

Project must provide baseline habitats, post-development habitat plan, metric assumptions, off-site units where relevant, and management plan.

land_rights_agent · Biodiversity net gain assessment provided · 89% confidence

Pass
Habitat management plan provided

Pass against LE012 (land_environment).

Project must include habitat creation, enhancement, management, monitoring, and maintenance responsibilities.

land_rights_agent · Habitat management plan provided · 89% confidence

Pass
Water body and river basin management plan checked

Pass against LE013 (land_environment).

Project must identify water bodies, river basin constraints, drainage pathways, pollution risks, and required mitigation.

land_rights_agent · Water body and river basin management plan checked · 89% confidence

Pass
Flood risk assessment provided

Pass against LE014 (land_environment).

Site package must include a flood-risk assessment or screening outcome appropriate for project location, flood zone, and technology.

land_rights_agent · Flood risk assessment provided · 90% confidence

Pass
Hydraulic modelling completed where required

Pass against LE015 (land_environment).

Where flood risk, watercourse interaction, or drainage complexity requires it, hydraulic modelling must be provided and referenced.

land_rights_agent · Hydraulic modelling completed where required · 90% confidence

Pass
Soil analysis completed

Pass against LE016 (land_environment).

Project must assess soil type, agricultural land classification, contamination risk, erosion risk, and construction handling requirements.

land_rights_agent · Soil analysis completed · 90% confidence

Pass
Hedgerow removal plan provided

Pass against LE017 (land_environment).

Where hedgerows are affected, project must assess loss, legal protections, replacement planting, biodiversity value, and timing constraints.

land_rights_agent · Hedgerow removal plan provided · 91% confidence

Pass
Arboricultural impact assessment provided

Pass against LE018 (land_environment).

Where trees are affected, project must include tree survey, root protection areas, method statement, and replacement planting.

land_rights_agent · Arboricultural impact assessment provided · 91% confidence

Pass
Air quality assessment provided

Pass against LE019 (land_environment).

Project must assess construction dust, traffic emissions, local air quality receptors, and mitigation.

land_rights_agent · Air quality assessment provided · 91% confidence

Pass
Planning consent granted or path defined

Pass against PL001 (planning).

Planning status must be granted or have a formally documented consent pathway with decision timeline.

planning_agent · Planning consent granted or path defined · 85% confidence

Pass
Correct permission route selected

Pass against PL002 (planning).

Submission must identify whether the project follows local planning, permitted development, DCO/NSIP, section 37, marine licence, or other relevant pathway.

planning_agent · Correct permission route selected · 86% confidence

Pass
Planning conditions are trackable

Pass against PL003 (planning).

Conditions attached to consent must be extracted and linked to accountable owners in delivery governance.

planning_agent · Planning conditions are trackable · 86% confidence

Pass
Community consultation report provided

Pass against PL004 (planning).

Project must evidence community consultation, issues raised, applicant responses, and resulting design or mitigation changes.

planning_agent · Community consultation report provided · 86% confidence

Pass
Design and access statement provided

Pass against PL006 (planning).

Where required, project must provide design rationale, site access logic, layout explanation, and inclusive access considerations.

planning_agent · Design and access statement provided · 87% confidence

Pass
Green belt assessment provided

Pass against PL007 (planning).

Where the site is in or near green belt, project must assess harm, exceptional circumstances, alternatives, and mitigation.

planning_agent · Green belt assessment provided · 87% confidence

Pass
Bundle.land Control Bundle.formed

land_control_bundle (4 docs)

Bundle assembled with 4 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.land Control Bundle.formed · 90% confidence

Pass
Bundle.planning Bundle.formed

planning_bundle (1 docs)

Bundle assembled with 1 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.planning Bundle.formed · 90% confidence

Pass
Bundle.technical Connection Bundle.formed

technical_connection_bundle (1 docs)

Bundle assembled with 1 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.technical Connection Bundle.formed · 90% confidence

Pass
Bundle.grid Model Bundle.formed

grid_model_bundle (3 docs)

Bundle assembled with 3 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.grid Model Bundle.formed · 90% confidence

Pass
Bundle.deliverability Bundle.formed

deliverability_bundle (1 docs)

Bundle assembled with 1 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.deliverability Bundle.formed · 90% confidence

Pass
Bundle.finance Bundle.formed

finance_bundle (1 docs)

Bundle assembled with 1 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.finance Bundle.formed · 90% confidence

Pass
Bundle.insurance Bundle.formed

insurance_bundle (2 docs)

Bundle assembled with 2 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.insurance Bundle.formed · 90% confidence

Pass
Bundle.corporate Authority Bundle.formed

corporate_authority_bundle (2 docs)

Bundle assembled with 2 document(s).

Clustered by primary-category match.

document_clusterer · Bundle.corporate Authority Bundle.formed · 90% confidence

Pass
Connection voltage declared and consistent

Pass against CN001 (connection).

Connection voltage must be declared and remain consistent across technical, planning, single-line diagram, and contractual documents.

technical_classification_agent · Connection voltage declared and consistent · 88% confidence

Pass
Export capacity within scheme limits

Pass against CN002 (connection).

Declared export capacity must remain within the submitted and approved scheme envelope.

technical_classification_agent · Export capacity within scheme limits · 89% confidence

Pass
Import capacity declared

Pass against CN003 (connection).

Project must declare import capacity requirements for auxiliary load, charging load, commissioning, and operational modes.

technical_classification_agent · Import capacity declared · 89% confidence

Pass
Single-line diagram provided

Pass against CN004 (connection).

Project must include a single-line diagram showing connection point, transformers, switchgear, protection, metering, and generation/storage assets.

technical_classification_agent · Single-line diagram provided · 89% confidence

Pass
Protection settings available

Pass against CN005 (connection).

Protection philosophy, settings, grading, interface protection, and trip schemes must be documented or marked as pending operator approval.

technical_classification_agent · Protection settings available · 90% confidence

Pass
Fault level assessment complete

Pass against CN006 (connection).

Project must assess fault level contribution and confirm it remains within local network equipment ratings or mitigation is defined.

technical_classification_agent · Fault level assessment complete · 90% confidence

Pass
Power quality assessment complete

Pass against CN007 (connection).

Project must assess harmonics, flicker, voltage step, voltage fluctuation, and compliance with applicable limits.

technical_classification_agent · Power quality assessment complete · 90% confidence

Pass
Active network management terms declared

Pass against CN008 (connection).

If connection is constrained or flexible, active network management terms, curtailment assumptions, and control obligations must be declared.

technical_classification_agent · Active network management terms declared · 91% confidence

Pass
Metering scheme defined

Pass against CN009 (connection).

Metering design must identify import/export metering, settlement metering, boundary points, communications, and ownership.

technical_classification_agent · Metering scheme defined · 91% confidence

Pass
Long-lead items identified

Pass against PR004 (procurement).

Procurement plan must identify long-lead equipment, delivery windows, reservation status, and supply-chain risk.

readiness_orchestrator · Long-lead items identified · 68% confidence

Pass
Warranty and performance guarantees provided

Pass against PR008 (procurement).

Major equipment contracts must include warranty, degradation, availability, performance, and defect liability terms.

readiness_orchestrator · Warranty and performance guarantees provided · 70% confidence

Pass
Construction method statement provided

Pass against CO001 (construction).

Construction pack must include method statements for access, civils, electrical works, lifting, commissioning, and reinstatement.

readiness_orchestrator · Construction method statement provided · 85% confidence

Pass
Safe materials confirmed

Pass against CO002 (construction).

Construction materials must meet relevant safety, fire, environmental, and durability requirements for the site and technology.

readiness_orchestrator · Safe materials confirmed · 86% confidence

Pass
Construction programme aligned to grid milestones

Pass against CO003 (construction).

Construction schedule must align with connection milestones, outage windows, commissioning dates, and energisation dependencies.

readiness_orchestrator · Construction programme aligned to grid milestones · 86% confidence

Pass
Traffic management plan provided

Pass against CO004 (construction).

Construction plan must include HGV routing, abnormal loads, road safety, traffic management, and local access mitigation.

readiness_orchestrator · Traffic management plan provided · 86% confidence

Pass
Construction environmental management plan provided

Pass against CO005 (construction).

Project must include a CEMP covering dust, noise, water, waste, ecology, working hours, spill response, and site controls.

readiness_orchestrator · Construction environmental management plan provided · 87% confidence

Pass
Fire safety plan provided

Pass against CO006 (construction).

For battery or electrical infrastructure, project must include fire safety strategy, emergency access, separation distances, suppression approach, and liaison evidence.

readiness_orchestrator · Fire safety plan provided · 87% confidence

Pass
EPC contractor qualified

Pass against PE002 (personnel).

EPC contractor must evidence relevant licences, accreditations, grid experience, insurance, and project references.

readiness_orchestrator · EPC contractor qualified · 73% confidence

Pass
Company authority to contract confirmed

Pass against LC001 (legal_compliance).

Applicant must evidence corporate authority to enter connection, land, procurement, financing, and construction agreements.

readiness_orchestrator · Company authority to contract confirmed · 84% confidence

Pass
Permits register complete

Pass against LC002 (legal_compliance).

Project must include a permits register covering planning, environmental, grid, highways, water, ecology, land, and construction approvals.

readiness_orchestrator · Permits register complete · 85% confidence

Pass
Blocking items resolved

Pass against RD001 (readiness).

No blocking criterion may remain failed before the project is marked ready for offer acceptance, financial close, or construction start.

readiness_orchestrator · Blocking items resolved · 90% confidence

Pass
Domain scores above threshold

Pass against RD002 (readiness).

Each domain must exceed the configured readiness threshold or be explicitly waived by an authorised reviewer.

readiness_orchestrator · Domain scores above threshold · 90% confidence

Pass
Overall readiness verdict

Pass against RD004 (readiness).

Aggregated verdict across domain checks; any blocking failure triggers a not-ready outcome.

readiness_orchestrator · Overall readiness verdict · 91% confidence

Pass
TSO consultation requirement checked

Pass against GC001 (grid_consultation).

Project must confirm whether TSO/NESO consultation is required based on capacity, voltage, transmission impact, and embedded generation rules.

export_compliance_agent · TSO consultation requirement checked · 83% confidence

Pass
DNO pre-application engagement completed

Pass against GC002 (grid_consultation).

Project must evidence DNO pre-application engagement, budget estimate, feasibility study, or connection application path.

export_compliance_agent · DNO pre-application engagement completed · 83% confidence

Pass
Statement of Works status declared

Pass against GC004 (grid_consultation).

Where applicable, project must state Statement of Works or transmission impact assessment status and any dependencies.

export_compliance_agent · Statement of Works status declared · 84% confidence

Pass

Document Bundles

Land Rights Bundle
4 docs
Coverage captured from submitted bundle evidence.
Available
Planning Bundle
1 docs
Coverage captured from submitted bundle evidence.
Available
Technical Bundle
1 docs
Coverage captured from submitted bundle evidence.
Available
Deliverability Bundle
1 docs
Coverage captured from submitted bundle evidence.
Available

Section Summaries

Project summarypass

Bernierburgh Wind Scheme (TAC-2026-0002). 16 documents in the current submission.

Document inventorypass

Documents span 9 categories: corporate_authority, correspondence, deliverability, finance, grid_model, insurance, land_rights, planning, technical.

Land rightsn/a

Land control evidence consistent across documents.

Planningn/a

Planning consent in date with conditions noted.

Technical pathwayn/a

Technical pack reviewed — SLD, protection and connection point present.

Export compliancefail

Evaluated 5 rule criteria from active pack 1.0.0.

Deliverabilityflag

Deliverability evidence light — transformer procurement noted.

Financepass

Finance commitment evidenced via EPC LoI.

Insurancepass

Insurance certificate in force.

Recommended decisionflag

Recommended decision: READY WITH FLAGS.

Deficiencies & Risks

Deliverability pack minimal

Deliverability bundle has no programme document attached.

MediumProvide clarifying evidence or a written explanation.
Overall readiness: ready_with_flags

Aggregated 8 bundles and 58 claims.

MediumProvide clarifying evidence or a written explanation.
Professional indemnity cover for key consultants

Risk identified against IN004 (insurance).

MediumAddress the issue and resubmit a corrected revision.
Policy expiry extends beyond construction start

Risk identified against IN005 (insurance).

HighAddress the issue and resubmit a corrected revision.
Insurance deductibles reflected in financial model

Risk identified against IN006 (insurance).

MediumProvide clarifying evidence or a written explanation.
Supplier is a valid trading company

Risk identified against PR001 (procurement).

HighAddress the issue and resubmit a corrected revision.
Supplier liquidity checked

Risk identified against PR002 (procurement).

HighAddress the issue and resubmit a corrected revision.
Procurement agreement valid through construction start

Risk identified against PR003 (procurement).

HighAddress the issue and resubmit a corrected revision.
Procurement spec declares grid-forming capability

Risk identified against PR005 (procurement).

HighProvide clarifying evidence or a written explanation.
Grid-following risk treatment disclosed

Risk identified against PR006 (procurement).

MediumProvide clarifying evidence or a written explanation.
Expansion capacity reserved where required

Risk identified against PR007 (procurement).

MediumProvide clarifying evidence or a written explanation.
Cyber security requirements included

Risk identified against PR009 (procurement).

HighProvide clarifying evidence or a written explanation.
Commissioning plan provided

Risk identified against CO007 (construction).

HighAddress the issue and resubmit a corrected revision.
Developer experience evidenced

Risk identified against PE001 (personnel).

MediumProvide clarifying evidence or a written explanation.
Principal designer and contractor named

Risk identified against PE003 (personnel).

HighProvide clarifying evidence or a written explanation.
Grid engineering lead assigned

Risk identified against PE004 (personnel).

MediumProvide clarifying evidence or a written explanation.
Environmental consultant appointed

Risk identified against PE005 (personnel).

MediumProvide clarifying evidence or a written explanation.
Responsibility matrix complete

Risk identified against PE006 (personnel).

MediumProvide clarifying evidence or a written explanation.
Material contracts signed or statused

Risk identified against LC003 (legal_compliance).

HighProvide clarifying evidence or a written explanation.
Sanctions screening complete

Risk identified against LC004 (legal_compliance).

BlockingAddress the issue and resubmit a corrected revision.
Data room index complete

Risk identified against LC005 (legal_compliance).

MediumProvide clarifying evidence or a written explanation.
Hazard identification complete

Risk identified against SA001 (safety).

HighProvide clarifying evidence or a written explanation.
Electrical safety rules defined

Risk identified against SA002 (safety).

HighProvide clarifying evidence or a written explanation.
Emergency response plan provided

Risk identified against SA003 (safety).

HighProvide clarifying evidence or a written explanation.
Site security plan provided

Risk identified against SA004 (safety).

MediumProvide clarifying evidence or a written explanation.
Safety zone assessment provided

Risk identified against SA005 (safety).

MediumProvide clarifying evidence or a written explanation.
O&M provider identified

Risk identified against OP001 (operations).

MediumAddress the issue and resubmit a corrected revision.
Availability assumptions supported

Risk identified against OP002 (operations).

MediumAddress the issue and resubmit a corrected revision.
Spare parts strategy provided

Risk identified against OP003 (operations).

LowAddress the issue and resubmit a corrected revision.
Monitoring and reporting defined

Risk identified against OP004 (operations).

MediumAddress the issue and resubmit a corrected revision.
Decommissioning responsibility assigned

Risk identified against OP005 (operations).

MediumAddress the issue and resubmit a corrected revision.
Evidence freshness checked

Risk identified against RD003 (readiness).

HighProvide clarifying evidence or a written explanation.
Land agreement valid through construction start

Risk identified against LE002 (land_environment).

HighProvide clarifying evidence or a written explanation.
Right-of-way plan provided

Risk identified against LE003 (land_environment).

HighProvide clarifying evidence or a written explanation.
Land plan boundary consistent

Risk identified against LE004 (land_environment).

HighAddress the issue and resubmit a corrected revision.
Third-party rights identified

Risk identified against LE005 (land_environment).

MediumAddress the issue and resubmit a corrected revision.
Noise and vibration assessment provided

Risk identified against LE020 (land_environment).

HighAddress the issue and resubmit a corrected revision.
Climate change assessment provided

Risk identified against LE021 (land_environment).

MediumAddress the issue and resubmit a corrected revision.
Socio-economic assessment provided

Risk identified against LE022 (land_environment).

MediumAddress the issue and resubmit a corrected revision.
Human health assessment provided

Risk identified against LE023 (land_environment).

MediumAddress the issue and resubmit a corrected revision.
Glint and glare assessed

Risk identified against LE024 (land_environment).

MediumAddress the issue and resubmit a corrected revision.
Statement of need provided

Risk identified against PL005 (planning).

MediumProvide clarifying evidence or a written explanation.
SCADA and communications design defined

Risk identified against CN010 (connection).

HighAddress the issue and resubmit a corrected revision.
Connection offer status declared

Risk identified against GC003 (grid_consultation).

HighProvide clarifying evidence or a written explanation.
Outage window coordination evidenced

Risk identified against GC005 (grid_consultation).

MediumAddress the issue and resubmit a corrected revision.