Evidence Zero
Procurement Letter 1 (v2)
Structured document preview (seed-rendered, same surface as the application report)
Long-lead procurement status letter
| Application reference | TAC-2026-0010 |
|---|---|
| Project | Adalbertofield Solar Scheme |
| Developer / client | Kilback - Veum SPV Ltd |
| Parent developer | Hudson, Feeney and Ernser |
| Document (as filed) | Procurement Letter 1 (v2) |
| Inferred type | procurement letter |
| Category | deliverability |
| Document date | 2026-08-04T07:35:55.000Z |
This letter summarises procurement status for Adalbertofield Solar Scheme (TAC-2026-0010) as at 2026-08-04T07:35:55.000Z. It is issued by the project’s delivery team to support deliverability review against Terrencefort BSP · 132 kV class interface and the target export capability of 73 MW (export).
| Package | Status | Commentary |
|---|---|---|
| HV transformers | RFQ issued | Delivery slot reserved Q4; final specs tied to TO model v3. |
| MV switchgear | Technical bid evaluation | Shortlist of two vendors; FAT dates proposed. |
| Inverters / PCS | Pre-order discussion | Harmonic compliance study loop with protection team. |
The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.
Reinforcement dependencies
Upstream works remain coordinated with the host operator programme. Any slippage beyond the window assumed in TAC-2026-0010 will be escalated under the governance protocol and reflected in the critical-path update.
Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.
Procurement Letter 1 (v2) — supporting appendix
This appendix (sheet 3) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-3 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-3 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-3 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-3 | Critical path through reinforcement, primary plant, and commissioning tests. |
HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.
Procurement Letter 1 (v2) — supporting appendix
This appendix (sheet 4) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-4 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-4 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-4 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-4 | Critical path through reinforcement, primary plant, and commissioning tests. |
Procurement Letter 1 (v2) — supporting appendix
This appendix (sheet 5) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-5 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-5 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-5 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-5 | Critical path through reinforcement, primary plant, and commissioning tests. |
Cited Extracts
[1] Procurement Letter 1 (v2) · p.2
Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.
[2] Procurement Letter 1 (v2) · p.1
The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.
[3] Procurement Letter 1 (v2) · p.3
HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.