Evidence Zero
Planning Decision Notice 5 (v4)
Structured document preview (seed-rendered, same surface as the application report)
Decision notice — grant of planning permission
| Application reference | TAC-2026-0010 |
|---|---|
| Project | Adalbertofield Solar Scheme |
| Developer / client | Kilback - Veum SPV Ltd |
| Parent developer | Hudson, Feeney and Ernser |
| Document (as filed) | Planning Decision Notice 5 (v4) |
| Inferred type | planning decision notice |
| Category | planning |
| Document date | 2026-08-04T07:35:55.000Z |
Local planning authority reference: PA/0010-2026. Permission is granted to Kilback - Veum SPV Ltd for development comprising solar_plus_bess and associated infrastructure at West Deondre Site: 45989 Wuckert Glen, Fort Jennyfer, in accordance with the plans listed in the schedule to the application.
Conditions
1. Construction hours: Monday–Friday 07:00–19:00, Saturday 08:00–13:00, excluding public holidays unless otherwise approved.
2. Ecology: habitat compensation areas to be established in accordance with the approved landscape and ecology management plan.
3. Noise: operational noise limits at nearest noise-sensitive receptors as set out in the environmental statement chapter 11.
Reasons for decision (summary)
The authority weighed landscape and visual effects, heritage assets, highway safety, and flood risk. Mitigation secured by condition addresses the main adverse effects to an acceptable degree. The development is consistent with development plan policies on renewable energy subject to compliance with conditions.
The proposal aligns with the declared export capacity (73 MW (export)) and the connection location described as Terrencefort BSP · 132 kV class interface for grid-related externalities assessed in the ES.
Planning Decision Notice 5 (v4) — supporting appendix
This appendix (sheet 3) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-3 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-3 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-3 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-3 | Critical path through reinforcement, primary plant, and commissioning tests. |
Planning Decision Notice 5 (v4) — supporting appendix
This appendix (sheet 4) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
Permission is granted to Kilback - Veum SPV Ltd for solar_plus_bess at West Deondre Site: 45989 Wuckert Glen, Fort Jennyfer.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-4 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-4 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-4 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-4 | Critical path through reinforcement, primary plant, and commissioning tests. |
The notice uses local planning language, while the connection context references 132 kV and Terrencefort BSP · 132 kV class interface.
Planning Decision Notice 5 (v4) — supporting appendix
This appendix (sheet 5) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
Conditions are listed, but no owner, due date, discharge status, or delivery governance reference is provided.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-5 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-5 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-5 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-5 | Critical path through reinforcement, primary plant, and commissioning tests. |
Planning Decision Notice 5 (v4) — supporting appendix
This appendix (sheet 6) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-6 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-6 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-6 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-6 | Critical path through reinforcement, primary plant, and commissioning tests. |
Planning Decision Notice 5 (v4) — supporting appendix
This appendix (sheet 7) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-7 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-7 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-7 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-7 | Critical path through reinforcement, primary plant, and commissioning tests. |
Planning Decision Notice 5 (v4) — supporting appendix
This appendix (sheet 8) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-8 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-8 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-8 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-8 | Critical path through reinforcement, primary plant, and commissioning tests. |
Cited Extracts
[1] Planning Decision Notice 5 (v4) · p.4
Permission is granted to Kilback - Veum SPV Ltd for solar_plus_bess at the land interests described in the application schedules.
[2] Planning Decision Notice 5 (v4) · p.4
The notice uses local planning language, while the connection context references 132 kV and Terrencefort BSP · 132 kV class interface.
[3] Planning Decision Notice 5 (v4) · p.5
Conditions are listed, but no owner, due date, discharge status, or delivery governance reference is provided.