UK DNO 1

Document Review

Review application documents and agent-cited evidence. TAC-2026-0010

Reviewing documents for Adalbertofield Solar Scheme

Bundle references

1 / 9

Evidence Zero

Planning Application 1 (v2)

Structured document preview (seed-rendered, same surface as the application report)

Planning application dossier — indexed submission

Application referenceTAC-2026-0010
ProjectAdalbertofield Solar Scheme
Developer / clientKilback - Veum SPV Ltd
Parent developerHudson, Feeney and Ernser
Document (as filed)Planning Application 1 (v2)
Inferred typeplanning application
Categoryplanning
Document date2026-08-04T07:35:55.000Z

This dossier records the principal planning submission components for Adalbertofield Solar Scheme (TAC-2026-0010) submitted by Kilback - Veum SPV Ltd. It reflects the development description, supporting studies, and drawing index issued for authority determination and related operator review.

Submission itemDoc refDescription
Application formPA-001Signed application form and ownership certificates.
Design & access statementPA-012Design rationale, constraints, and access strategy.
Environmental statementPA-030Topic chapters and non-technical summary.
Site plansPA-042Location, red-line, and access plans in controlled revision.

Development summary

The application seeks consent for solar_plus_bess with associated access, cabling, drainage, and temporary construction compounds at West Deondre Site: 45989 Wuckert Glen, Fort Jennyfer. The submission assumes export capability of 73 MW (export) and a grid interface at Terrencefort BSP · 132 kV class interface.

Consultation and revisions

Pre-application consultations were undertaken with planning, highways, and ecology officers. Revisions include landscape buffer adjustments, construction traffic routing updates, and phased habitat management commitments.

Schedule of principal plans

Plan titleRevisionPurpose
Location planRev CDemonstrates site extent and surrounding context.
Red-line planRev DDefines planning boundary and access corridors.
Layout planRev BIndicative plant arrangement and cable corridors.
Construction logisticsRev ATemporary works, compounds, and haul routes.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 4) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-4Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-4Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-4Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-4Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 5) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-5Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-5Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-5Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-5Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 6) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-6Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-6Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-6Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-6Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 7) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

The planning register confirms validation and fee payment for the full application family.

WorkstreamCross-refOperator review notes
Land & accessLA-7Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-7Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-7Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-7Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 8) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-8Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-8Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-8Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-8Critical path through reinforcement, primary plant, and commissioning tests.

The dossier records pre-application consultation with planning, highways, and ecology officers and describes design revisions.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 9) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

The dossier explains project components but does not clearly separate need, grid benefit, and policy alignment.

WorkstreamCross-refOperator review notes
Land & accessLA-9Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-9Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-9Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-9Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 10) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-10Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-10Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-10Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-10Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 11) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-11Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-11Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-11Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-11Critical path through reinforcement, primary plant, and commissioning tests.

Planning Application 1 (v2) — supporting appendix

This appendix (sheet 12) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-12Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-12Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-12Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-12Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Planning Application 1 (v2) · p.8

    The dossier records pre-application consultation with planning, highways, and ecology officers and describes design revisions.

  • [2] Planning Application 1 (v2) · p.7

    The planning register confirms validation and fee payment for the full application family.

  • [3] Planning Application 1 (v2) · p.9

    The dossier explains project components but does not clearly separate need, grid benefit, and policy alignment.