GridLayer Operator View
UK DNO 1

Document Review

Review application documents and agent-cited evidence. TAC-2026-0010

Reviewing documents for Adalbertofield Solar Scheme

Bundle references

1 / 1

Evidence Zero

Procurement Letter 1 (v2)

Structured document preview (seed-rendered, same surface as the application report)

Long-lead procurement status letter

Application referenceTAC-2026-0010
ProjectAdalbertofield Solar Scheme
Developer / clientKilback - Veum SPV Ltd
Parent developerHudson, Feeney and Ernser
Document (as filed)Procurement Letter 1 (v2)
Inferred typeprocurement letter
Categorydeliverability
Document date2026-08-04T07:35:55.000Z

This letter summarises procurement status for Adalbertofield Solar Scheme (TAC-2026-0010) as at 2026-08-04T07:35:55.000Z. It is issued by the project’s delivery team to support deliverability review against Terrencefort BSP · 132 kV class interface and the target export capability of 73 MW (export).

PackageStatusCommentary
HV transformersRFQ issuedDelivery slot reserved Q4; final specs tied to TO model v3.
MV switchgearTechnical bid evaluationShortlist of two vendors; FAT dates proposed.
Inverters / PCSPre-order discussionHarmonic compliance study loop with protection team.

The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.

Reinforcement dependencies

Upstream works remain coordinated with the host operator programme. Any slippage beyond the window assumed in TAC-2026-0010 will be escalated under the governance protocol and reflected in the critical-path update.

Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.

Procurement Letter 1 (v2) — supporting appendix

This appendix (sheet 3) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-3Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-3Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-3Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-3Critical path through reinforcement, primary plant, and commissioning tests.

HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.

Procurement Letter 1 (v2) — supporting appendix

This appendix (sheet 4) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-4Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-4Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-4Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-4Critical path through reinforcement, primary plant, and commissioning tests.

Procurement Letter 1 (v2) — supporting appendix

This appendix (sheet 5) supplements TAC-2026-0010 for Adalbertofield Solar Scheme. It cross-references the declared export capability (73 MW (export)), the technology mix (solar_plus_bess), and the connection scope at Terrencefort BSP · 132 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-5Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-5Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-5Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-5Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Procurement Letter 1 (v2) · p.2

    Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.

  • [2] Procurement Letter 1 (v2) · p.1

    The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.

  • [3] Procurement Letter 1 (v2) · p.3

    HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.