Evidence Zero

Procurement Letter 1

Structured document preview (seed-rendered, same surface as the application report)

Long-lead procurement status letter

Application referenceTAC-2026-0005
ProjectPort Gabriella Storage Scheme
Developer / clientBernier LLC SPV Ltd
Parent developerLegros, Howe and Rodriguez
Document (as filed)Procurement Letter 1
Inferred typeprocurement letter
Categorydeliverability
Document date2026-06-07T11:23:08.000Z

This letter summarises procurement status for Port Gabriella Storage Scheme (TAC-2026-0005) as at 2026-06-07T11:23:08.000Z. It is issued by the project’s delivery team to support deliverability review against Wolftown BSP · 66 kV class interface and the target export capability of 35 MW (export).

PackageStatusCommentary
HV transformersRFQ issuedDelivery slot reserved Q4; final specs tied to TO model v3.
MV switchgearTechnical bid evaluationShortlist of two vendors; FAT dates proposed.
Inverters / PCSPre-order discussionHarmonic compliance study loop with protection team.

Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.

Reinforcement dependencies

Upstream works remain coordinated with the host operator programme. Any slippage beyond the window assumed in TAC-2026-0005 will be escalated under the governance protocol and reflected in the critical-path update.

Procurement Letter 1 — supporting appendix

This appendix (sheet 3) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.

WorkstreamCross-refOperator review notes
Land & accessLA-3Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-3Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-3Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-3Critical path through reinforcement, primary plant, and commissioning tests.

The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.

Procurement Letter 1 — supporting appendix

This appendix (sheet 4) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-4Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-4Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-4Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-4Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Procurement Letter 1 · p.3

    The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.

  • [2] Procurement Letter 1 · p.3

    HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.

  • [3] Procurement Letter 1 · p.1

    Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.