GridLayer Operator View
UK DNO 1

Document Review

Review application documents and agent-cited evidence. TAC-2026-0005

Reviewing documents for Port Gabriella Storage Scheme

Bundle references

1 / 14

Evidence Zero

Red Line Boundary Plan 10

Structured document preview (seed-rendered, same surface as the application report)

Red-line boundary plan — controlled extract

Application referenceTAC-2026-0005
ProjectPort Gabriella Storage Scheme
Developer / clientBernier LLC SPV Ltd
Parent developerLegros, Howe and Rodriguez
Document (as filed)Red Line Boundary Plan 10
Inferred typered line boundary plan
Categoryland rights
Document date2026-06-07T11:23:08.000Z

This extract identifies the proposed development boundary for Port Gabriella Storage Scheme (TAC-2026-0005) at Haltom City Site: 550 Hardy Lake, Haleyshire. The red-line extent is recorded as 80 acres and should be read alongside title and access plans in the land bundle.

Plan elementCodeDescription
Development extentRL-01Primary generation and ancillary infrastructure boundary (edged red).
Access corridorRL-02Construction and operational access route to public highway.
Cable route optionRL-03Indicative export cable alignment to connection interface.
Exclusion zoneRL-04Sensitive habitat and offset zone excluded from permanent works.

The plan marks an access track but does not identify affected third-party rights, public rights of way, or wayleave counterparties.

Coordinate and annotation references

Coordinate geometry and parcel overlays are maintained in the GIS source package. This PDF extract is a controlled representation for review and traceability; engineering set-out must use the survey-grade source files.

The red-line plan identifies the development extent, access corridor, cable route option, and exclusion zones for Haltom City Site: 550 Hardy Lake, Haleyshire.

Boundary checks for readiness review

- Confirm red-line area is consistent with land option/lease acreage assumptions.

- Verify access and easement corridors are represented in ownership evidence.

- Confirm planning submission plans and technical layout plans reference the same boundary revision.

The access corridor is shown as RL-02, but the easement owner and wayleave instrument are not named on the plan.

Red Line Boundary Plan 10 — supporting appendix

This appendix (sheet 3) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-3Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-3Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-3Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-3Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Red Line Boundary Plan 10 · p.2

    The red-line plan identifies the development extent, access corridor, cable route option, and exclusion zones for the land interests described in the application schedules.

  • [2] Red Line Boundary Plan 10 · p.2

    The access corridor is shown as RL-02, but the easement owner and wayleave instrument are not named on the plan.

  • [3] Red Line Boundary Plan 10 · p.1

    The plan marks an access track but does not identify affected third-party rights, public rights of way, or wayleave counterparties.