GridLayer Operator View
UK DNO 1

Document Review

Review application documents and agent-cited evidence. TAC-2026-0005

Reviewing documents for Port Gabriella Storage Scheme

Bundle references

1 / 12

Evidence Zero

Lease Agreement 1

Structured document preview (seed-rendered, same surface as the application report)

Agreement for lease

Application referenceTAC-2026-0005
ProjectPort Gabriella Storage Scheme
Developer / clientBernier LLC SPV Ltd
Parent developerLegros, Howe and Rodriguez
Document (as filed)Lease Agreement 1
Inferred typelease agreement
Categoryland rights
Document date2026-06-07T11:23:08.000Z

THIS AGREEMENT is made on 2026-06-07T11:23:08.000Z between (1) Ridgeway Landholdings LLP (Landlord) and (2) Bernier LLC SPV Ltd (Tenant) in respect of the project site known as Haltom City Site: 550 Hardy Lake, Haleyshire.

1. Grant

Subject to satisfaction of conditions precedent, the Landlord agrees to grant and the Tenant agrees to take a lease of the Premises in the form annexed at schedule 2.

2. Conditions precedent

1. Planning permission and associated consents becoming implementable in accordance with statutory requirements.

2. Connection arrangements progressing in line with the programme assumptions in the application pack.

3. Evidence of funding and insurance for construction phase obligations.

3. Term, rent, and review

The lease term shall commence on the completion date and continue for thirty-five (35) years unless terminated earlier. Base rent, indexation mechanics, and review dates are set out in schedule 3.

4. Tenant covenants

The Tenant covenants to operate and maintain the plant in accordance with law, maintain insurance, and comply with environmental and reinstatement obligations in schedule 5.

5. Alienation and charging

Assignment or underletting is permitted only to qualifying transferees with landlord consent not to be unreasonably withheld. Security assignments to lenders are permitted under a direct agreement framework.

6. Reinstatement and yield-up

At expiry or earlier termination, the Tenant shall reinstate and remediate in accordance with the decommissioning plan and any agreed residual infrastructure carve-outs.

Lease Agreement 1 — supporting appendix

This appendix (sheet 4) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-4Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-4Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-4Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-4Critical path through reinforcement, primary plant, and commissioning tests.

Lease Agreement 1 — supporting appendix

This appendix (sheet 5) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-5Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-5Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-5Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-5Critical path through reinforcement, primary plant, and commissioning tests.

The lease term appears to cover construction, but break clauses and landlord termination for grid delay are cross-referenced to schedules not attached.

Lease Agreement 1 — supporting appendix

This appendix (sheet 6) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-6Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-6Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-6Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-6Critical path through reinforcement, primary plant, and commissioning tests.

Lease Agreement 1 — supporting appendix

This appendix (sheet 7) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-7Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-7Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-7Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-7Critical path through reinforcement, primary plant, and commissioning tests.

Lease Agreement 1 — supporting appendix

This appendix (sheet 8) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-8Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-8Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-8Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-8Critical path through reinforcement, primary plant, and commissioning tests.

Schedule plans omit the cable routing strip shown on the operator red-line pack, so the demise may not include the full export route.

Lease Agreement 1 — supporting appendix

This appendix (sheet 9) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-9Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-9Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-9Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-9Critical path through reinforcement, primary plant, and commissioning tests.

Lease Agreement 1 — supporting appendix

This appendix (sheet 10) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-10Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-10Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-10Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-10Critical path through reinforcement, primary plant, and commissioning tests.

Lease Agreement 1 — supporting appendix

This appendix (sheet 11) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-11Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-11Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-11Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-11Critical path through reinforcement, primary plant, and commissioning tests.

Lease Agreement 1 — supporting appendix

This appendix (sheet 12) supplements TAC-2026-0005 for Port Gabriella Storage Scheme. It cross-references the declared export capability (35 MW (export)), the technology mix (solar_pv), and the connection scope at Wolftown BSP · 66 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

The lease demises the project land to Bernier LLC SPV Ltd for the purpose of constructing and operating solar_pv.

WorkstreamCross-refOperator review notes
Land & accessLA-12Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-12Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-12Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-12Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Lease Agreement 1 · p.12

    The lease demises the project land to Bernier LLC SPV Ltd for the purpose of constructing and operating solar_pv.

  • [2] Lease Agreement 1 · p.5

    The lease term appears to cover construction, but break clauses and landlord termination for grid delay are cross-referenced to schedules not attached.

  • [3] Lease Agreement 1 · p.8

    Schedule plans omit the cable routing strip shown on the operator red-line pack, so the demise may not include the full export route.