GridLayer Operator View
UK DNO 1

Document Review

Review application documents and agent-cited evidence. TAC-2026-0007

Reviewing documents for Cicero Wind Scheme

Bundle references

1 / 11

Evidence Zero

Protection Statement 10 (v2)

Structured document preview (seed-rendered, same surface as the application report)

Protection philosophy and grading summary

Application referenceTAC-2026-0007
ProjectCicero Wind Scheme
Developer / clientBins - Kub SPV Ltd
Parent developerWiza Group
Document (as filed)Protection Statement 10 (v2)
Inferred typeprotection statement
Categorytechnical
Document date2026-05-06T17:42:12.000Z

This controlled extract supports TAC-2026-0007 for Cicero Wind Scheme. It must be read with the latest connection offer assumptions, fault level study, and earthing design. Declared export capability: 30 MW (export). Technology: bess_export. Interface: West Ronaldoside Primary · 33 kV class interface.

Relay functions, grading references, and interface protection files are identified in the protection extract.

Drawing / doc no.TAC-2026-0007-TEC-PROTECTION-01
RevisionC — issued for connection review
AuthorAuthorised technical representative

Key parameters (representative)

- Primary plant ratings and protection zones cross-referenced to relay setting files in the confidential appendix.

- Selectivity between incomer, transformer HV, and feeder protection maintained for minimum fault contributions.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 3) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-3Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-3Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-3Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-3Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 4) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-4Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-4Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-4Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-4Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 5) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-5Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-5Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-5Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-5Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 6) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-6Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-6Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-6Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-6Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 7) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-7Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-7Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-7Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-7Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 8) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-8Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-8Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-8Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-8Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 9) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-9Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-9Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-9Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-9Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 10) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-10Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-10Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-10Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-10Critical path through reinforcement, primary plant, and commissioning tests.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 11) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-11Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-11Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-11Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-11Critical path through reinforcement, primary plant, and commissioning tests.

Harmonic compliance is referenced, but source model assumptions are provisional.

Protection Statement 10 (v2) — supporting appendix

This appendix (sheet 12) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

Fault-level results are marked pending and no equipment-rating mitigation is defined.

WorkstreamCross-refOperator review notes
Land & accessLA-12Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-12Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-12Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-12Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Protection Statement 10 (v2) · p.1

    Protection grading study and recommended settings appended.

  • [2] Protection Statement 10 (v2) · p.1

    Relay functions, grading references, and interface protection files are identified in the protection extract.

  • [3] Protection Statement 10 (v2) · p.12

    Fault-level results are marked pending and no equipment-rating mitigation is defined.

  • [4] Protection Statement 10 (v2) · p.11

    Harmonic compliance is referenced, but source model assumptions are provisional.