Evidence Zero

Transformer Datasheet 5

Structured document preview (seed-rendered, same surface as the application report)

Main power transformer — technical datasheet extract

Application referenceTAC-2026-0007
ProjectCicero Wind Scheme
Developer / clientBins - Kub SPV Ltd
Parent developerWiza Group
Document (as filed)Transformer Datasheet 5
Inferred typetransformer datasheet
Categorytechnical
Document date2026-05-06T17:42:12.000Z

This controlled extract supports TAC-2026-0007 for Cicero Wind Scheme. It must be read with the latest connection offer assumptions, fault level study, and earthing design. Declared export capability: 30 MW (export). Technology: bess_export. Interface: West Ronaldoside Primary · 33 kV class interface.

Drawing / doc no.TAC-2026-0007-TEC-TRANSFORMER-01
RevisionC — issued for connection review
AuthorAuthorised technical representative

Key parameters (representative)

- Primary plant ratings and protection zones cross-referenced to relay setting files in the confidential appendix.

- Selectivity between incomer, transformer HV, and feeder protection maintained for minimum fault contributions.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 3) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

The datasheet identifies warranty-backed ratings, operating envelopes, and defect-liability assumptions.

WorkstreamCross-refOperator review notes
Land & accessLA-3Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-3Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-3Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-3Critical path through reinforcement, primary plant, and commissioning tests.

Reactive capability is described, but grid-forming mode is not expressly labelled.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 4) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-4Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-4Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-4Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-4Critical path through reinforcement, primary plant, and commissioning tests.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 5) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

Factory acceptance testing, sea freight, and site receipt windows are stated relative to contractual delivery dates.

WorkstreamCross-refOperator review notes
Land & accessLA-5Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-5Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-5Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-5Critical path through reinforcement, primary plant, and commissioning tests.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 6) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-6Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-6Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-6Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-6Critical path through reinforcement, primary plant, and commissioning tests.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 7) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-7Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-7Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-7Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-7Critical path through reinforcement, primary plant, and commissioning tests.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 8) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-8Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-8Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-8Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-8Critical path through reinforcement, primary plant, and commissioning tests.

Transformer Datasheet 5 — supporting appendix

This appendix (sheet 9) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-9Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-9Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-9Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-9Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Transformer Datasheet 5 · p.3

    The datasheet identifies warranty-backed ratings, operating envelopes, and defect-liability assumptions.

  • [2] Transformer Datasheet 5 · p.5

    Factory acceptance testing, sea freight, and site receipt windows are stated relative to contractual delivery dates.

  • [3] Transformer Datasheet 5 · p.3

    Reactive capability is described, but grid-forming mode is not expressly labelled.