Document Review

Review application documents and agent-cited evidence. TAC-2026-0007

Reviewing documents for Cicero Wind Scheme

Bundle references

1 / 14

Evidence Zero

Correspondence 4 (v3)

Structured document preview (seed-rendered, same surface as the application report)

Project correspondence log and extracts

Application referenceTAC-2026-0007
ProjectCicero Wind Scheme
Developer / clientBins - Kub SPV Ltd
Parent developerWiza Group
Document (as filed)Correspondence 4 (v3)
Inferred typecorrespondence
Categorycorrespondence
Document date2026-04-10T16:27:02.000Z

This correspondence pack collates principal clarifications and responses for Cicero Wind Scheme (TAC-2026-0007) exchanged between the project team and reviewing parties in support of readiness assessment.

DateRefSummary
2026-02-10COR-014Clarification on transformer procurement lead times and FAT witness windows.
2026-02-17COR-018Updated red-line and access drawing cross-reference issued.
2026-02-25COR-022Response to planning condition discharge query.

Several email threads end with “we will revert” without a dated connection-offer status or modification reference.

Extracted correspondence themes

- Programme dependencies and long-lead procurement timing.

- Boundary, land rights, and title consistency checks.

- Technical assumptions used in network studies and protection submissions.

The correspondence log records clarifications exchanged with reviewing parties on transformer lead times, red-line drawings, and planning conditions.

Correspondence 4 (v3) — supporting appendix

This appendix (sheet 3) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

No outage requirements, network access windows, or commissioning access constraints are stated.

WorkstreamCross-refOperator review notes
Land & accessLA-3Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-3Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-3Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-3Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] Correspondence 4 (v3) · p.2

    The correspondence log records clarifications exchanged with reviewing parties on transformer lead times, red-line drawings, and planning conditions.

  • [2] Correspondence 4 (v3) · p.1

    Several email threads end with “we will revert” without a dated connection-offer status or modification reference.

  • [3] Correspondence 4 (v3) · p.3

    No outage requirements, network access windows, or commissioning access constraints are stated.