Long-lead procurement status letter
| Application reference | TAC-2026-0007 |
|---|---|
| Project | Cicero Wind Scheme |
| Developer / client | Bins - Kub SPV Ltd |
| Parent developer | Wiza Group |
| Document (as filed) | Procurement Letter 1 (v4) |
| Inferred type | procurement letter |
| Category | deliverability |
| Document date | 2026-05-06T17:42:12.000Z |
This letter summarises procurement status for Cicero Wind Scheme (TAC-2026-0007) as at 2026-05-06T17:42:12.000Z. It is issued by the project’s delivery team to support deliverability review against West Ronaldoside Primary · 33 kV class interface and the target export capability of 30 MW (export).
HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.
| Package | Status | Commentary |
|---|---|---|
| HV transformers | RFQ issued | Delivery slot reserved Q4; final specs tied to TO model v3. |
| MV switchgear | Technical bid evaluation | Shortlist of two vendors; FAT dates proposed. |
| Inverters / PCS | Pre-order discussion | Harmonic compliance study loop with protection team. |
Reinforcement dependencies
Upstream works remain coordinated with the host operator programme. Any slippage beyond the window assumed in TAC-2026-0007 will be escalated under the governance protocol and reflected in the critical-path update.
Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.
Procurement Letter 1 (v4) — supporting appendix
This appendix (sheet 3) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-3 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-3 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-3 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-3 | Critical path through reinforcement, primary plant, and commissioning tests. |
Procurement Letter 1 (v4) — supporting appendix
This appendix (sheet 4) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-4 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-4 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-4 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-4 | Critical path through reinforcement, primary plant, and commissioning tests. |
Procurement Letter 1 (v4) — supporting appendix
This appendix (sheet 5) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-5 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-5 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-5 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-5 | Critical path through reinforcement, primary plant, and commissioning tests. |
Procurement Letter 1 (v4) — supporting appendix
This appendix (sheet 6) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-6 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-6 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-6 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-6 | Critical path through reinforcement, primary plant, and commissioning tests. |
Cited Extracts
[1] Procurement Letter 1 (v4) · p.1
HV transformers, MV switchgear, and inverter/PCS packages are named with reservation or evaluation status.
[2] Procurement Letter 1 (v4) · p.5
The transformer reservation is stated to lapse on 2026-06-15, before planned construction start on 2026-07-01.
[3] Procurement Letter 1 (v4) · p.2
Inverter discussions reference harmonic study loops but do not state whether operation is grid-forming or grid-following.