Review application documents and agent-cited evidence. TAC-2026-0007

Reviewing documents for Cicero Wind Scheme

Bundle references

1 / 11

Evidence Zero

EPC Engagement Letter 2 (v3)

Structured document preview (seed-rendered, same surface as the application report)

PRIVATE & CONFIDENTIAL

Engineering, procurement and construction — engagement letter

Application referenceTAC-2026-0007
ProjectCicero Wind Scheme
Developer / clientBins - Kub SPV Ltd
Parent developerWiza Group
Document (as filed)EPC Engagement Letter 2 (v3)
Inferred typeepc letter
Categoryfinance
Document date2026-05-06T17:42:12.000Z

The contractor is named, appointed for pre-construction services, and tied to design, procurement, HSE, commissioning, and handover scope.

Date: 2026-05-06T17:42:12.000Z

To: Bins - Kub SPV Ltd Attn: Project director — delivery Re: Cicero Wind Scheme (TAC-2026-0007)

We, Harbourbeck Construction & Energy Limited (“Contractor”), are pleased to set out the basis on which we will progress pre-construction services and, subject to contract, full EPC delivery for the bess_export scheme at Macyfield Site: 365 Bogan Mountains, Lake Gustaveton. This letter supplements the connection application pack and is intended to evidence commercial engagement for lender and operator diligence.

1. Background and reliance

The Client is developing Cicero Wind Scheme with a target export capability of 30 MW (export) at West Ronaldoside Primary · 33 kV class interface. The Contractor has reviewed outline layouts, single-line diagrams, and the preliminary protection philosophy supplied under TAC-2026-0007. The parties acknowledge that the connection offer and any construction direction from the host network operator may impose further design constraints after financial close.

Commissioning strategy is mentioned, but no accountable owners, witness-test dates, or energisation procedure are provided.

2. Appointment

The Client appoints the Contractor to provide the services described in section 3 on an exclusive basis until either (a) a full EPC contract is executed or (b) this letter is terminated in accordance with section 9. Until such EPC contract exists, fees are payable as set out in section 5.

The letter is subject to contract and commercial terms remain indicative.

3. Scope of services (pre-construction and EPC-ready)

1. Detailed design development for generation plant, balance of plant, MV collection, and grid interface up to the demarcation point stated in the connection offer for Cicero Wind Scheme.

2. Procurement planning, long-lead equipment reservation (transformers, inverters / PCS, switchgear), and construction methodology including laydown and access from the site address above.

3. HSE planning, construction phase plan outline, and quality plan aligned to CDM 2015 and Client governance.

4. Commissioning strategy including energisation sequence, witness tests, and handover data packs for operations.

3A. Exclusions (unless added by change instruction)

- Offshore transmission, shared cable corridors outside the red-line boundary, and reinforcement works upstream of the point of connection.

- Development consent beyond the planning position declared in the application, and any section agreement not yet in agreed form.

- Lender step-in mechanics — the Contractor will co-operate with reasonable information requests but does not assume advisory duties to funders.

4. Programme milestones

The following dates are planning assumptions for TAC-2026-0007 and will be baselined at EPC contract signature. They are stated to support readiness reviews and evidence that delivery windows have been socialised with the supply chain.

MilestoneTarget windowDependencies
Notice to proceed (NTP)T0 + 8 weeksFinancial close, insurances, and land access in force.
Mechanical completion (MC)T0 + 22 monthsEquipment deliveries, civils, and primary electrical installation.
Energisation / first exportT0 + 28 monthsGrid compliance tests, protection witness, and DNO / TO permissions.
Provisional acceptance (PAC)T0 + 31 monthsSnag closure, as-built records, and training to Client O&M.

The Contractor will maintain a critical-path report monthly and flag any float erosion attributable to connection offer changes, late land releases, or third-party reinforcement delays.

5. Commercial framework (headline terms)

Unless otherwise agreed, the Contractor proposes a lump-sum EPC price envelope subject to defined contingencies for ground conditions and for network study iterations. Pre-construction services will be invoiced monthly on a time-and-materials basis capped at an agreed ceiling, with fifty percent (50%) creditable against the EPC lump sum upon contract signature within nine (9) months of this letter.

Liquidated damages for delay to PAC shall not exceed a negotiated percentage of the contract price; bonus milestones may be included for early export capability where grid windows permit.

Retention5% to PAC, one-half released at PAC, balance at FAC.
VATUK VAT rules as applicable; tax treatment of imported equipment per project structure.
CurrencyPounds sterling unless the EPC agreement specifies dual-currency tranches for major equipment.

6. Liens, performance security, and subcontracting

The Contractor shall not assert statutory or contractual liens over Client assets except where payment is demonstrably overdue and unresolved for thirty (30) days after notice. Performance security shall be provided in the form of an on-demand bond for a percentage of the contract price as agreed in the EPC contract. Major subcontractors for electrical and civils packages require Client consent (not unreasonably withheld) where packages exceed agreed thresholds.

7. HSE, quality, and environmental compliance

The Contractor will implement an ISO 45001-aligned safety management system, maintain design reviews under a gated technical assurance plan, and track environmental permit conditions including noise limits during construction and dust suppression on access routes.

8. Insurance

- Contractors’ all risks including transit, offshore marine where not excluded, and advanced loss of profits as agreed.

- Employer’s liability and public liability at not less than industry-standard limits for projects of this scale.

- Professional indemnity for design errors and omissions, maintained for the defect notification period.

9. Default and termination

Either party may terminate for material breach if uncured within thirty (30) days of written notice. Termination for convenience is permitted only as expressly set out in the EPC contract; prior to EPC signature, either party may terminate this engagement letter on fourteen (14) days’ notice, paying fees due for accepted work to date.

10. Governing law and dispute resolution

This letter is governed by the laws of England and Wales. The parties will seek resolution in good faith, then mediation, prior to litigation in the courts of England and Wales.

11. Counterparts and signatures

For and on behalf of the Client

Name: ___________________________

Title: ___________________________

Date: ____________________________

For and on behalf of the Contractor

Harbourbeck Construction & Energy Limited

Name: ___________________________

Title: ___________________________

Date: ____________________________

EPC Engagement Letter 2 (v3) — supporting appendix

This appendix (sheet 7) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-7Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-7Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-7Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-7Critical path through reinforcement, primary plant, and commissioning tests.

EPC Engagement Letter 2 (v3) — supporting appendix

This appendix (sheet 8) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.

WorkstreamCross-refOperator review notes
Land & accessLA-8Verify red-line, access rights, and any wayleave assumptions against latest survey.
Planning & consentPC-8Confirm commencement conditions and discharge of pre-commencement items.
Electrical designEL-8Align SLD, protection, and fault level study with latest DNO / TO model version.
ProgrammePR-8Critical path through reinforcement, primary plant, and commissioning tests.

Cited Extracts

  • [1] EPC Engagement Letter 2 (v3) · p.1

    The letter is subject to contract and commercial terms remain indicative.

  • [2] EPC Engagement Letter 2 (v3) · p.1

    Commissioning strategy is mentioned, but no accountable owners, witness-test dates, or energisation procedure are provided.

  • [3] EPC Engagement Letter 2 (v3) · p.1

    The contractor is named, appointed for pre-construction services, and tied to design, procurement, HSE, commissioning, and handover scope.