Certificate of insurance — construction phase
| Application reference | TAC-2026-0007 |
|---|---|
| Project | Cicero Wind Scheme |
| Developer / client | Bins - Kub SPV Ltd |
| Parent developer | Wiza Group |
| Document (as filed) | Insurance Certificate 1 (v2) |
| Inferred type | insurance certificate |
| Category | insurance |
| Document date | 2026-05-06T17:42:12.000Z |
This certificate evidences policies in force for works relating to Cicero Wind Scheme (TAC-2026-0007) at Macyfield Site: 365 Bogan Mountains, Lake Gustaveton. Limits and deductibles are stated below and are subject to the full policy wordings.
| Insured | Bins - Kub SPV Ltd |
|---|---|
| Broker | Cairnholm Risk Partners Ltd |
| CAR policy no. | CAR-TAC20260-UK |
| Public liability limit | GBP 50,000,000 any one occurrence |
| Employers’ liability | GBP 10,000,000 any one claim |
Endorsements and loss payees
Loss payee endorsements shall be issued in favour of Meridian Project Finance Limited and any additional parties listed in the credit agreement. Delay in start-up cover is included subject to a waiting period of ninety (90) days.
Operational phase rollover
Upon PAC, operational all-risks and business interruption policies will roll in with a sum insured indexed to 30 MW (export) and declared technology (bess_export).
Deductibles and waiting periods are listed, but the certificate does not show whether they are carried through the financial downside case.
Insurance Certificate 1 (v2) — supporting appendix
This appendix (sheet 3) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
The policy expiry date is 2026-06-15, before planned construction start on 2026-07-01, and no renewal undertaking is attached.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-3 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-3 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-3 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-3 | Critical path through reinforcement, primary plant, and commissioning tests. |
Insurance Certificate 1 (v2) — supporting appendix
This appendix (sheet 4) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
CAR policy CAR-TAC20260-UK is listed for construction works at Macyfield Site: 365 Bogan Mountains, Lake Gustaveton.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-4 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-4 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-4 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-4 | Critical path through reinforcement, primary plant, and commissioning tests. |
Upstream and downstream liabilities are referenced with aggregate limits and a schedule of principal endorsements.
Insurance Certificate 1 (v2) — supporting appendix
This appendix (sheet 5) supplements TAC-2026-0007 for Cicero Wind Scheme. It cross-references the declared export capability (30 MW (export)), the technology mix (bess_export), and the connection scope at West Ronaldoside Primary · 33 kV class interface. Figures in the operator-facing pack may supersede this extract where stamped “controlled copy”.
Public liability is scheduled at £10,000,000 any one occurrence for Cicero Wind Scheme construction and operations phases.
| Workstream | Cross-ref | Operator review notes |
|---|---|---|
| Land & access | LA-5 | Verify red-line, access rights, and any wayleave assumptions against latest survey. |
| Planning & consent | PC-5 | Confirm commencement conditions and discharge of pre-commencement items. |
| Electrical design | EL-5 | Align SLD, protection, and fault level study with latest DNO / TO model version. |
| Programme | PR-5 | Critical path through reinforcement, primary plant, and commissioning tests. |
Cited Extracts
[1] Insurance Certificate 1 (v2) · p.5
Public liability is scheduled at £10,000,000 any one occurrence for Cicero Wind Scheme construction and operations phases.
[2] Insurance Certificate 1 (v2) · p.4
Upstream and downstream liabilities are referenced with aggregate limits and a schedule of principal endorsements.
[3] Insurance Certificate 1 (v2) · p.4
CAR policy CAR-TAC20260-UK is listed for construction works at the land interests described in the application schedules.
[4] Insurance Certificate 1 (v2) · p.3
The policy expiry date is 2026-06-15, before planned construction start on 2026-07-01, and no renewal undertaking is attached.
[5] Insurance Certificate 1 (v2) · p.2
Deductibles and waiting periods are listed, but the certificate does not show whether they are carried through the financial downside case.